Lock-block dyke wall and concrete box culvert outlet beside a creek
All projects

Reach 8 Dyke

Owner
City of Burnaby
Location
Burnaby, BC
Consultant
Associated Engineering
Construction period
June 2019 – August 2021
Contract value
$6,576,900

Key scope of work

  • Construction of approximately 950 m of new dyke
  • 4 m wide dyke crest with 3:1 side slopes
  • Lock-block retaining walls
  • New floodbox at Glenlyon Creek
  • Micropile and reinforced concrete watermain crossing
  • Trail paving
  • Culvert and storm sewer installation
  • Signage and handrails
  • Sand preload and ground improvements
  • Associated civil and site servicing works